On August 8 Network Security Science and Technology Museum in Zhengzhou
Time:2020-11-02 
分享到:
0

On August 10, after 208 days of struggle, the construction and exhibition arrangement were completed. The Science and Technology Museum of Zhengzhou Bauhinia Science and Technology Park passed the joint acceptance of the completion as scheduled and obtained the real estate property right certificate, which broke the record of key project construction in Zhengzhou High-tech Zone and witnessed the strength of Jingu and the responsibility of jingu people with facts!

It dates back to June 2019.In last year's "strong network cup" a game for a while to show series of activities, the high-tech zone officer xuan: will be based on a comprehensive strength, location of tian jian lake, converged network security personnel resources advantage, technology, industry, construction of the whole industry chain high-tech zone - Chinese redbud network information security technology park, landmark building zhengzhou west network security science and technology museum, comprehensive high-tech field, network space, and for the "strong network cup" competition, BBS, exhibition provides a permanent site.

Since then, the high-tech zone has put the construction of the network security science and technology Museum on the important agenda. More than 100 experts from academia, industry, exhibition and related departments have been united to conduct integrated research and demonstration on architectural design, functional design and operation management.The construction plan and the Exhibition plan were also highly appraised by wu Jiangxing, Shen Changxiang, Wang Xiaoyun and other industry experts.

An excellent scheme needs an equally excellent performer. Since the "2020 Net Cup" competition will be held in September, the project must be completed no later than September 1st. Such a complicated design and urgent time limit is enough to make most contractors shrink back.To give up this honor?The people of henan should not be disappointed. With confidence in their own strength, jingu group took over the written pledge to fulfill a military order.

January 4, 2020 is a memorable day for Henan Bauhinia Science and Technology Park.As the construction side of the project, after the tense preparation and careful deployment in the early stage, the construction team of Jingu Group rushed into the field, and a battle against time began.

In order to ensure the venue on time delivery, the company developed science and technology museum construction of the whole chain scheduling table, chart, inversion period, every step will be the construction plan and accurate to hours and minutes, make hundreds of working procedure, 12 internal team, 21 external team, more than 2600 cooperated-builing personnel can be unified coordination and close cooperation, to ensure that the planning and design, solution preparation, site construction, resources guarantee seamless, synchronized advancement.

However, just 20 days after construction began, the coVID-19 outbreak completely disrupted the orderly construction schedule.The site was closed in early February to comply with the country's anti-epidemic order.The resulting shortage of supplies, the inability of staff to return to The city, and limited logistics would have dealt a fatal blow to the completion of the project. Despair was palpable.Group leaders, through a video conference call, instructed all Jingu employees not to give up hope and to calm down and wait for the time to return to work.

At the beginning of March, the outbreak of the epidemic finally eased.Under the care of provincial and municipal leaders at all levels and with the active assistance and coordination of the Operation Center of High-tech Zone, steel structure, SP floor and other materials needed for the project construction were successively admitted, and more than 300 construction personnel returned to work on the basis of ensuring their health.At the same time, the whole construction site also opened epidemic prevention mode, set infrared thermometer in the office area and workers' living area, at the same time to achieve disinfection, safety, sanitation three "full coverage", do everything possible to plug the epidemic loophole.

The 186 days of coVID-19 prevention and control and the resumption of work and production, accounting for 90% of the construction period, were taken into account by jingu employees. Without a single case of virus infection, the foundation construction of the project was completed on January 18, 2020, 7 days ahead of schedule.Subject acceptance shall be completed on April 7, 2020, 15 days in advance;The comprehensive acceptance will be completed on August 10, 2020, and the overall project will be completed successfully.

High-tech zone working committee secretary, director of xin-ting wang said when mentioned venues, this is "team spirit, fighting spirit, the spirit of craftsman, self-sacrifice spirit" of a thorough practice, but also learn more xi general secretary for all staff to reply important elements group spirit, the spirit of the letter into a vivid reflection of the strong driving force ".

The floorage of 18742 m2, 1.2 tons of design drawings, the 208 - day period, the groups of figures behind is not only reflect the jingu person fearless and pay, also highlights the ministry to bring the huge advantage of prefabricated building system, jingu person at the completion of the henan mission entrusted by the people at the same time, also again writing speed legend in the field of Chinese architecture.